BAGUIO CITY (PIA) — The National Commission on Indigenous Peoples-Cordillera Administrative Region (NCIP-CAR) ensures that indigenous cultural communities (ICCs) and indigenous peoples (IPs) have a say in development projects affecting their ancestral domains through the Free, Prior, and Informed Consent (FPIC) process.
Atty. Wilson K. Kalangeg, chief of the NCIP-CAR Technical and Management Services Division, said Section 59 of Republic Act No. 8371, or the Indigenous Peoples’ Rights Act (IPRA) of 1997, requires consultation and community consent before proponents can secure permits, licenses, or agreements for projects within ancestral domains.
“The community has also the right to say no to any project,” Kalangeg said during the Usapang PIA on Nov. 12.
He clarified that the NCIP facilitates the process to safeguard and protect the IPs’ rights by ensuring a process free from coercion and undue influence while respecting customary laws, indigenous political structures, and community decision-making authority.
Kalangeg explained that the process starts with a Field-Based Investigation (FBI) where the NCIP identifies the ancestral domain areas affected by a project, validates information from the proponent, and documents the community’s elders and customary decision-making practices.
After the investigation, the NCIP conducts two community assemblies. The first explains IPs’ rights under IPRA and validates the FBI findings while the second allows the project proponent to present the proposed project and answers the community’s questions. The community may also invite experts to explain the project in detail.
The process then moves to consensus-building where community members discuss and decide on the proposal using their customary laws and practices.
“In the FPIC guidelines, the consensus-building must be in accordance with the customary law and practices,” Kalangeg said.
He cited the tungtungan system, a traditional Cordillera practice where community members discuss issues to reach a collective decision. He emphasized that the process does not necessarily require majority voting.
If the community rejects the proposal, the NCIP issues a resolution of non-consent. The proponent may file a motion for reconsideration, which the community will decide on. If the community approves the project, the NCIP facilitates negotiations between the community and the proponent.
The negotiations result in a memorandum of agreement (MOA) the NCIP must present and translate into the community’s language for review and comments before signing.
Kalangeg also clarified that community consent is separate from the landowner’s permission. A project cannot proceed if either the community rejects it or the landowner refuses to allow the use of the property.
He said the NCIP may also conduct further validation and extend negotiations to address complaints and concerns raised by community members.
Kalangeg emphasized that following the FPIC guidelines protects IPs rights and ensures their decisions reflect their customary practices.
The NCIP is conducting nationwide orientations, capacity development workshops, and alignment seminars on the newly approved NCIP Administrative Order No. 3, series of 2026, or the 2026 FPIC Guidelines, which will replace the 2012 guidelines. **JDP/DEG-PIA CAR w/ GIP Floribel Sad-o